Congratulations on the successful trial operation of high-voltage substations and transmission line built by SPTTC
Congratulations on the successful trial operation of high-voltage substations and transmission line built by SPTTC
On the occasion of the 70th anniversary of the founding of the People's Republic of China,two substations and one transmission line built by Sichuan Electric Power Transmission and Transformation Construction Co., Ltd was successfully put into trial operation, which was a significant milestone in the construction of Cote d’Ivoire Cote d'Ivoire Power Grid Development and Rehabilitation Project, a milestone celebrated by all the members of the company’s project team.
The two substations are Sérébou 225kV Substation and Bondoukou 225kV Substation, and the transmission line isSérébou-Bondoukou 225kV Transmission Line. They are part of Cote d'Ivoire Power Grid Development and Rehabilitation Project – Lot 1 which has being constructed by the company as the construction subcontractor with CMEC as the contractor.
热烈庆祝塞黑布、邦杜库变电站一次性带电成功
在全国人民热烈庆祝祖国母亲70周年之际,我司同时迎来了西非片区项目的里程碑日子,全体成员热烈庆祝塞黑布、邦杜库变电站一次性带电成功,献礼祖国70华诞。
由我公司承建的科特迪瓦电网发展和改造Ⅰ区域Sérébou225kV变电站、Bondoukou225kV变电站及Sérébou-Bondoukou225kV输电线路经过48小时不间断送电,最终于2019年10月3日全站一次性带电成功。