Dakar-90 kV Power Distribution Network Project
来源: 发布时间:2017/11/1 16:59:07 点击率:939
Senegal
Senagal is the country where SPTTC’s first overseas branch is located.
The Senagal project, on which SPTTC and the prime contractor, CMEC/Sinomach, cooperated for the first time, won high praise from the owner SENELEC and CMEC/Sinomach, which built a sound foundation for SPTTC’s further market development in West Africa and an increased cooperation with CMEC.
Project Name | le projet de La Boucle 90kV de Dakar (le projet de Réseau de Distribution de Courant Electrique de 90 KV de Dakar) Dakar 90 kV Power Distribution Network Project |
Project Description | Construction of four substations and interconnection of the four substations with double-circuit 90 kV buried cables with a total route length of 27km. |