Uganda-contract for the installation and commissioning of the industrial park substation & remote ends
来源: 发布时间:2017/11/1 17:13:09 点击率:1114
The installation and commissioning of the industrial park substation & remote ends of Uganda is the second project in East Africa. The project involved four 132/33kv substation which is Luzira substation(Lot B1)、Mukonosubstation(Lot B2)、Iganga substation(Lot B3)、Namanve South substation(Lot B4), and telecommunication upgrade project of national MCC, 33.672km 132kv transmission lines and replace 56.25km OPGW lines.
Project Name | The installation and commissioning of the industrial park substation & remote ends of Uganda |
Project Description | The project involved four 132/33kv substation which is Luzira substation(Lot B1)、Mukonosubstation(Lot B2)、Iganga substation(Lot B3)、Namanve South substation(Lot B4), and telecommunication upgrade project of national MCC, 33.672km 132kv transmission lines and replace 56.25km OPGW lines |