PROJECTS

Home-PROJECTS-PROJECTS

Genale Dawa-III-Yirgalem-II-Wolayita Sodo-II (GDYW-II) 400kV Transmission Line Project

来源:      发布时间:2017/11/1 15:36:05     点击率:908

Genale Dawa-III-Yirgalem-II-Wolayita Sodo-II (GDYW-II) 400kV Transmission Line Project

The project was successfully and substantially completed in just one year with fast speed.


Project Name

Genale Dawa-III-Yirgalem-II-Wolayita Sodo-II (GDYW-II) 400kV Transmission Line Project
Project DescriptionConstruction of 400kV Genale Dawa-III-Yirgalem-II-Wolayita Sodo-II Transmission Line Project (355 km in total length, of which 155.23 km was constructed by SPTTC), including right-of-way clearing, civil works, erection, stringing, commissioning and acceptance.